Thursday, March 5, 2009

Cold Construction


Ice Dams and snow build up on roof after 16" of snow and below freezing temperatures.

Here is the parking lot after 16 inches of snow fall over several weeks.

Here is the parking lot after hauling away 5 truck loads of snow.







Sunday, November 16, 2008

Bergig II November 15, 2008




Outside of building is complete. Inside improvements have begun.
Posted by Picasa

Bergig II October 15, 2008




Railing installed on upper deck. Elevator shaft finished and ready for elevator delivery.
Posted by Picasa

Bergig II September 13, 2008




Roofing finished, Columns and rockwork continues. Almost complete with stucco and staining on backside of building.
Posted by Picasa

Bergig II September 3, 2008




Rockwork begins. Windows are installed and stucco is being installed on the backside of the building
Posted by Picasa

Bergig II August 29, 2008




New tranformer arrives, roofing continues as well as outside finishes. Inside framing begins as windows and doors are installed.
Posted by Picasa

Bergig II August 18, 2008




Decking and columns have began. Roofers have started felting and applying shingles
Posted by Picasa